Royal Cornwall Hospital car park changes and roadworks
From May 2024
As we prepare our site for the new Women and Children’s Hospital, we can expect significant parking and access disruption, with limits on parking spaces. There are also likely to be delays getting in and out of the car parks, particularly at the start and end of the day.
Please see information below for a full breakdown of the works.
We apologise for any inconvenience caused during these works. If you have any questions, please email: rcht.buildingprogramme@nhs.net
Gravel Pit Staff Car Park Extension
Extension to create 176 more spaces. Work continues. 100% complete by July.
New Visitor Car Park D (mid 2024)
Work to complete and car park to open for visitor parking before car park 1A is closed.
Work continues on the Northern Access Road (NAR) March 2024 to March 2025
New road layout to create a main “artery” route into and out of Langarth. The road will be widened, new permanent pathways will be created.
Link Corridor, north side (May onwards)
Parking lost due to temporary Cardiac Catheter Lab being brought on-site.
Full closure of Car Park 1A (mid 2024 – mid 2026)
Enabling work to start for the new Pathology Building, next to Microbiology. New route into the hospital will be created, including bus stops and drop-off areas. Partial reopening only, and renamed Car Park A.